1140 Early Learning and Childcare building work updates

How we are improving our nurseries and building new ones

We are continuing to work really hard to ensure that all children can access their full 1140 hours early learning and childcare entitlement as soon as possible.

Our building works were on track to be completed for August 2020, however work had to stop during lockdown due to the coronavirus pandemic. Building contractors were able to start working again during the early summer, however this has meant our buildings would not be ready in time for the start of the new school year.

All nurseries in Renfrewshire are able to provide 1140 hours of early learning and childcare to the majority of children, however a small number of children are currently receiving the legal minimum of 600 hours and will move onto the expanded hours after building works at their nursery have been completed. You can see the expected completion dates for building works below.

For the three new build nurseries at Dargavel, Kirklandneuk and Lochfield, children are attending a local nursery and will have the option to move into the new build once it's ready.


Our plan for Renfrewshire nurseries

Our building designs meet the Scottish Government's Quality Action Plan for the Expansion of Early Learning and Childcare in Scotland and have been developed with council officers, education professionals and the Care Inspectorate.

Our biggest projects are building four new centres in Dargavel, Houston, Kirklandneuk and Lochfield ELCCs and three major extensions for Inchinnan and Kilbarchan community nurseries and St Margaret's ELCC.

We are also undertaking minor building works at Auchenlodment, Bridge of Weir, East Fulton, Ferguslie, Gallowhill, Glenburn, Glendee, Glenfield, Heriot, Lochwinnoch, Mossvale, Paisley, Ralston, St Anne's, St Catherine's, Todholm, and West Johnstone, Williamsburgh ELCCs.


Building works in progress

New build centres

Expected completion date

Dargavel ELCC, Bishopton

July 2021

Houston ELCC

January 2021

Kirklandneuk ELCC, Renfrew

January 2021

Lochfield ELCC, Paisley

March 2021

 

Extensions to existing classes and community nurseries

Expected completion date

Glendee ELCC, Renfrew

November 2020

Inchinnan Community Nursery

January 2021

Kilbarchan Community Nursery

November 2020

St Catherine's ELCC, Paisley

August 2021

St Margaret's ELCC, Johnstone

November 2020

Williamsburgh ELCC, Paisley

November 2020

 

Refurbishment of existing centres and classes

Expected completion date

Gallowhill ELCC, Paisley

November 2020

Glenburn ELCC, Paisley

December 2020

Lochwinnoch ELCC

January 2021

Ralston ELCC, Paisley

December 2020

St Anne's ELCC, Erskine

August 2021


Completed works

Refurbishment works have been completed for the following classes and centres.

  • Auchenlodment ELCC, Johnstone
  • Bridge of Weir ELCC
  • East Fulton ELCC, Linwood
  • Ferguslie ELCC, Paisley
  • Glenfield ELCC, Linwood
  • Heriot ELCC, Paisley
  • Mossvale ELCC, Paisley
  • Paisley ELCC
  • Todholm ELCC, Paisley